VPI Immingham B OCGT
- Connection date
- 16 Jan 2026
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 7 Aug 2020
VPI Immingham OCGT (EN010097) · Source: Planning Inspectorate - Technology
- Gas (OCGT)
- Total capacity
- 299 MW
- Connected now
- 0 MW
- Still to connect
- 299 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000854
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Apr 2025 registerTechnology changed from Gas engines to Gas (OCGT)
- 31 May 2024 registerConnection date moved from 30 Sep 2024 to 16 Jan 2026 (+16 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Humber Refinery 400kV to Humber Refinery 400kV Substation)
Also at Humber Refinery 400kV Substation
Substation view1 other project, 349 MW still to connect at this substation in total.