Tir Mostyn

BayWa r.e. OperatioNo Services Limited at Connahs Quay

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
1 Jun 2005
Status
Connected
Planning consent
Granted 19 Dec 2002
Denbighshire, reference 25/710/99/PF · Source: REPD
Customer
BayWa r.e. OperatioNo Services Limited
Site name
Tir Mostyn
Address
B4501 Cerrig Road, NoaNotyglyNo, Denbigh, North Wales, LL16 5RN
Grid reference
Easting 300360, northing 359426
Licence area
Merseyside, Cheshire and North Wales (SPM)
Grid supply point
Connahs Quay
Bulk supply point
HOLYWELL GT1 / RHYL GT1 / ST ASAPH GT2 / ST ASAPH GT4
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 21.25 MW registered
Registered capacity
21.25 MW
Maximum export capacity
21.25 MW
Maximum import capacity
0 MW
Flexible connection
Not stated
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
1300053834691
Import MPAN
1300053834682
Last updated
11 Nov 2020
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Connahs Quay

GSP view

31 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 459 MW: 281 MW connected, 178 MW accepted to connect.

See all 31

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.