QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Sandy Brow Lane (Spencers Farm)

Balance Power Projects Limited. at Kirkby

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2024
Status
Accepted to connect
Customer
Balance Power Projects Limited.
Site name
Sandy Brow Lane (Spencers Farm)
Address
off North Perimeter Road, Kirkby, Merseyside, L33 3AN
Grid reference
Easting 344270, northing 399858
Licence area
Merseyside, Cheshire and North Wales (SPM)
Grid supply point
Kirkby
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Storage
Energy source 1
Stored Energy, Storage - Electrochemical (Batteries): 82.8 MW registered
Registered capacity
82.8 MW
Change to maximum export capacity
82.8 MW
Change to maximum import capacity
82.8 MW
Flexible connection
Not stated
In a connection queue
Yes
Date accepted
Not stated
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
26 Jun 2026
Tracked since
June 2026 edition

Change history

Tracked since the June 2026 edition, across 4 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Kirkby

GSP view

13 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 298 MW: 69 MW connected, 229 MW accepted to connect.

See all 13

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose