Hawthorne Road

At Lister Drive

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not stated
Status
Accepted to connect
Planning consent
Granted 29 Mar 2022
Sefton, reference DC/2020/00085 · Source: REPD
Customer
Not stated
Site name
Hawthorne Road
Address
Hawthorne Road, Bootle, Bootle, Merseyside
Grid reference
Easting 334652, northing 396250
Licence area
Merseyside, Cheshire and North Wales (SPM)
Grid supply point
Lister Drive
Bulk supply point
BOOTLE GT2A / BURLINGTON ST GT1 / LISTER DV A GT2
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Storage
Energy source 1
Stored Energy, Storage - Electrochemical (Batteries): 20 MW registered
Registered capacity
20 MW
Change to maximum export capacity
20 MW
Change to maximum import capacity
8 MW
Flexible connection
Not stated
In a connection queue
Yes
Date accepted
Not stated
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
29 Nov 2024
Tracked since
March 2026 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Lister Drive

GSP view

12 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 76.3 MW: 56.3 MW connected, 20 MW accepted to connect.

  • Carnegie RoadShawEnergi Ltd, StorageConnected20 MW
  • Liverpool Int Bus ParkLeep Utilities, Gas and other fossil, Liverpool International Business Park primaryConnected13.5 MW
  • Royal Liverpool HospitialDalkia Utilities Services Plc, Gas and other fossil, ROYAL LIVERPOOL HOSP T1 / ROYAL LIVERPOOL HOSP T2 primaryConnected5 MW
  • Everton FC BESSESDL UK Ltd, StorageConnected4 MW
  • Liverpool UniversityUniversity Of Liverpool, Gas and other fossil, EDGE HILL T1 / LIVERPOOL UNIVERSITY T1 / LIVERPOOL UNIVERSITY T2 / LIVERPOOL UNIVERSITY T3 primaryConnected3.6 MW
  • John Lennon AirportJohn Lennon Airport, Solar, AIRPORT/ALDERWOOD AVE/HAREFIED ROAD primaryConnected3 MW
  • MATERNITY HOSPITALEquans Services Ltd, Gas and other fossil, BEAUMONT ST T1 / DINGLE VALE T1 / LARK LA T1 / MDHB BRUNSWICK DOCK T1 primaryConnected1.6 MW
  • NWWA Sandon DockUnited Utilities Group plc, Bioenergy and waste, BROOK ST T1 / KINGSWAY TUNNEL T1 / NWWA SANDON DOCK T1 / NWWA SANDON DOCK T2 primaryConnected1.4 MW

See all 12

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.