Carsecreugh Windfarm

John Laing Environmental Assets Group/ Reg Power Management at Glenluce

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
15 Jan 2014
Status
Connected
Planning consent
Granted 3 May 2011
Dumfries and Galloway, reference 06/P/1/0113 · Source: REPD
Customer
John Laing Environmental Assets Group/ Reg Power Management
Site name
Carsecreugh Windfarm
Address
Carscreugh Renewable Energy Park, Carscreugh Fell, Glenluce, Dumfries and Galloway, DG8 0PA
Grid reference
Easting 225000, northing 555000
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Glenluce
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 15.3 MW registered
Registered capacity
15.3 MW
Maximum export capacity
15.3 MW
Maximum import capacity
0 MW
Flexible connection
No
In a connection queue
No
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
1800060652463
Import MPAN
1800060652454
Last updated
14 Jul 2020
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Glenluce

GSP view

7 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 145 MW: 111 MW connected, 34 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.