Alwens Forest

Innogy Renewables Uk Ltd at St Asaph

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Dec 2027
Status
Accepted to connect
Planning consent
Granted 2 Oct 2025
Welsh Government (NSIP), reference DNS/3214855 · Source: REPD
Customer
Innogy Renewables Uk Ltd
Site name
Alwens Forest
Address
Alwen Reservoir Cerrigydrudion, Corwen, North Wales, LL21 9TT
Grid reference
Easting 296254, northing 353765
Licence area
Merseyside, Cheshire and North Wales (SPM)
Grid supply point
St Asaph
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 32.5 MW registered
Registered capacity
32.5 MW
Change to maximum export capacity
32.5 MW
Change to maximum import capacity
0 MW
Flexible connection
Not stated
In a connection queue
Yes
Date accepted
19 Apr 2018
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Jul 2020
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at St Asaph

GSP view

5 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 341 MW: 226 MW connected, 115 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.