Distribution / SPEN / Grid supply point

Tongland

Grid supply point in Central and Southern Scotland (SPD)

SPEN Embedded Capacity Register >1MW, September 2026 edition

The register spells this grid supply point more than one way: “Tongland” (4 sites) and “Tongland 11kV” (1 site).

5sites of 1 MW and over
184 MWcapacity
36 MWconnected (2 sites)
148 MWaccepted to connect (3 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage2118 MW–118 MW
Hydro and marine133 MW33 MW–
Solar130 MW–30 MW
Wind12.4 MW2.4 MW–

Storage capacity in MWh: not published by SPEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated12.4 MW–
Not stated433 MW148 MW

Search and filter all 5 sites at Tongland

What changed recently

Changes to sites here found in both editions of each pair, newest first.

August 2026 edition to September 2026 edition: 5 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.

  • St Marys Isle Solar FarmAugust 2026 editionTarget energisation date moved from 27 Jan 2030 to 27 Jun 2030 (5 months later)
  • GlenfarmMay 2026 editionFlexible connection changed from “no” to “yes”
  • GlenfarmMay 2026 editionIn a connection queue changed from “no” to “yes”
  • St Marys Isle Solar FarmMay 2026 editionTarget energisation date moved from 27 Feb 2030 to 27 Jan 2030 (1 month earlier)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.