STRATH OYKEL WIND FARM 77.6MW
At SHIN
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2032
- Status
- Accepted to connect
- Planning consent
- Granted 8 Jan 2025
Scottish Government (S36), reference ECU00003246 · Source: REPD - Customer
- Not stated
- Site name
- STRATH OYKEL WIND FARM 77.6MW
- Address
- ROSEHALL, DOUNE, HIGHLAND, IV27 4HE
- Grid reference
- Easting 241576, northing 901053
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- SHIN
- Bulk supply point
- Not stated
- Primary substation
- SHIN GRID
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- WIND, ONSHORE WIND TURBINES: 77.6 MW registered
- Registered capacity
- 77.6 MW
- Change to maximum export capacity
- 77.6 MW
- Change to maximum import capacity
- 5.5 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 7 Nov 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- December 2023 edition
Change history
Tracked since the December 2023 edition, across 36 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2025 editionTarget energisation date stated as 31 Oct 2032 (not stated in the October 2025 edition)
Also at SHIN
GSP view5 other sites at this grid supply point in the November 2026 edition, 5 of them at SHIN GRID, the same primary substation. In all, the sites here total 253 MW: 41 MW connected, 212 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.
How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.