LAND AT MANOR FARM
DNO CONSULTING LTD at LOVEDEAN GSP
SSEN Embedded Capacity Register, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 Jul 2026
- Status
- Accepted to connect
- Customer
- DNO CONSULTING LTD
- Site name
- LAND AT MANOR FARM
- Address
- LAND AT MANOR FARM, SHRIPNEY, BOGNOR REGIS, WEST SUSSEX, PO22 9UP
- Grid reference
- Easting 493499, northing 102153
- Licence area
- Southern England (SEPD)
- Grid supply point
- LOVEDEAN GSP
- Bulk supply point
- CHICHESTER
- Primary substation
- CHICHESTER
- Connection voltage
- 33 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 3.5 MW registered
- Registered capacity
- 3.5 MW
- Change to maximum export capacity
- 3.5 MW
- Change to maximum import capacity
- 0.168 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 4 May 2022
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- December 2025 edition
Change history
Tracked since the December 2025 edition, across 10 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at LOVEDEAN GSP
GSP view58 other sites at this grid supply point in the September 2026 edition, 5 of them at CHICHESTER, the same primary substation. In all, the sites here total 1.1 GW: 0.3 GW connected, 0.8 GW accepted to connect.
- TANGMERE AIRFIELD NURSERIES LIMITEDTANGMERE AIRFIELD NURSERIES LIMITED, Bioenergy and waste, CHICHESTER primaryConnected6.65 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose