ADD CAP FOR FEF201, 1MW EXPORT, 1MW IMPORT
At LUNANHEAD
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 22 Jul 2027
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- ADD CAP FOR FEF201, 1MW EXPORT, 1MW IMPORT
- Address
- CRAIGNATHRO FARM, FORFAR, ANGUS, DD8 2LE
- Grid reference
- Easting 346134, northing 748907
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- LUNANHEAD
- Bulk supply point
- Not stated
- Primary substation
- LUNANHEAD GRID
- Connection voltage
- 132 kV
- Technology group
- Wind
- Energy source 1
- WIND, ONSHORE WIND TURBINES: 1 MW registered
- Registered capacity
- 1 MW
- Change to maximum export capacity
- 1 MW
- Change to maximum import capacity
- 1 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 22 Jul 2026
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 7 Aug 2026
- Tracked since
- August 2026 edition
Change history
Tracked since the August 2026 edition, across 4 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at LUNANHEAD
GSP view13 other sites at this grid supply point in the November 2026 edition, 5 of them at LUNANHEAD GRID, the same primary substation. In all, the sites here total 452 MW: 7 MW connected, 445 MW accepted to connect.
- LAND OFF THE B9134 - BESSNAREC DISTRIBUTED ENERGY LTD, Storage, LUNANHEAD GRID primaryAccepted49.99 MW
- LAND OFF THE B9134 - ELECTRICAL ENERGYNAREC DISTRIBUTED ENERGY LTD, Other or not statedAccepted49.99 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?