CARSE GRAY ESTATE BESS+WIND

GRID TEAM BSR ENERGY at LUNANHEAD

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
15 Aug 2032
Status
Accepted to connect
Customer
GRID TEAM BSR ENERGY
Site name
CARSE GRAY ESTATE BESS+WIND
Address
LAND AT LUNANHEAD, FORFAR, FORFAR, ANGUS, DD8 5ES
Grid reference
Easting 336700, northing 755039
Licence area
North of Scotland (SHEPD)
Grid supply point
LUNANHEAD
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 75 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 60 MW registered
Registered capacity
75 MW
Change to maximum export capacity
60 MW
Change to maximum import capacity
60 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
15 Aug 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
September 2024 edition

Change history

Tracked since the September 2024 edition, across 27 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 15 Aug 2032 (not stated in the October 2025 edition)

Also at LUNANHEAD

GSP view

13 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 452 MW: 7 MW connected, 445 MW accepted to connect.

See all 13

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?