ACHANALT BATTERY ENERGY STORAGE SYSTEM
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2027
- Status
- Accepted to connect
- Customer
- ADTEK LTD
- Site name
- ACHANALT BATTERY ENERGY STORAGE SYSTEM
- Address
- ACHANALT, ACHANALT, GARVE, HIGHLAND, IV23 2QD
- Grid reference
- Easting 224521, northing 861552
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- GRUDIE BRIDGE
- Bulk supply point
- Not stated
- Primary substation
- GRUDIE BRIDGE
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 49.9 MW registered
- Registered capacity
- 49.9 MW
- Change to maximum export capacity
- 49.9 MW
- Change to maximum import capacity
- 52.526 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 4 Jul 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- September 2023 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the September 2023 edition, across 39 editions.
Changes to the details QueueWatch tracks, newest first.
- November 2025 editionTarget energisation date stated as 31 Oct 2027 (not stated in the October 2025 edition)
Also at GRUDIE BRIDGE
GSP view22 other sites at this grid supply point in the November 2026 edition, 19 of them at GRUDIE BRIDGE, the same primary substation. In all, the sites here total 215 MW: 55 MW connected, 160 MW accepted to connect.
- GRUDIE BRIDGE POWER STATIONSSE GENERATION LTD, Hydro and marine, GRUDIE BRIDGE primaryConnected12.54 MW
- GRUDIE BRIDGE POWER STATIONSSE GENERATION LTD, Hydro and marine, GRUDIE BRIDGE primaryConnected11.4 MW
- WYVIS HYDRO PROJECTSWYVIS ONE ESTATE LIMITED, Hydro and marine, GRUDIE BRIDGE primaryConnected3.705 MW
- ATTADALE HYDRO GENERATING STATIONHONISTER ENERGY LIMITED, Wind, GRUDIE BRIDGE primaryConnected3.5 MW
- ACHANALT POWER STATIONSSE GENERATION LTD, Other or not stated, GRUDIE BRIDGE primaryConnected2.945 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?