QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

50MW

OPDE UK LTD at BRORA

SSEN Embedded Capacity Register, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2030
Status
Accepted to connect
Customer
OPDE UK LTD
Site name
50MW
Address
CROFT 180/181, CLYNELISH MUIR CLYNELISH, BRORA, HIGHLAND, KW9 6LR
Grid reference
Easting 289624, northing 905373
Licence area
North of Scotland (SHEPD)
Grid supply point
BRORA
Bulk supply point
Not stated
Primary substation
BRORA GRID
Connection voltage
33 kV
Technology group
Other or not stated
Energy source 1
OTHER, OTHER: 52.68 MW registered
Registered capacity
52.68 MW
Change to maximum export capacity
50 MW
Change to maximum import capacity
52.632 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
6 Jul 2022
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 38 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at BRORA

GSP view

1 other site at this grid supply point in the September 2026 edition, 1 of them at BRORA GRID, the same primary substation. In all, the sites here total 138 MW: 138 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose