QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

MID CRAIGIE INDUSTRIAL ESTATE

At MILTON OF CRAIGIE

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Dec 2026
Status
Accepted to connect
Customer
Not stated
Site name
MID CRAIGIE INDUSTRIAL ESTATE
Address
PLOT 5, KINGSWAY EAST, DUNDEE, DUNDEE CITY, DD4 7RP
Grid reference
Easting 342595, northing 731993
Licence area
North of Scotland (SHEPD)
Grid supply point
MILTON OF CRAIGIE
Bulk supply point
Not stated
Primary substation
MILTON OF CRAIGIE GRID
Connection voltage
33 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 50 MW registered
Registered capacity
50 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
52.632 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
12 Jan 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Dec 2026 (not stated in the October 2025 edition)

Also at MILTON OF CRAIGIE

GSP view

5 other sites at this grid supply point in the November 2026 edition, 4 of them at MILTON OF CRAIGIE GRID, the same primary substation. In all, the sites here total 147 MW: 22 MW connected, 125 MW accepted to connect.

  • MIDMILL GASHOLDER STATIONVITAL ENERGI SOLUTIONS LIMITED, Storage, MILTON OF CRAIGIE GRID primaryAccepted49.9 MW
  • WELLBANKGREENTECH PROJECTS HOLDING UK LIMITED, Solar, MILTON OF CRAIGIE GRID primaryAccepted25 MW
  • BALDOVIE EFW LINE 3MVV ENVIRONMENT BALDOVIE LIMITED, Bioenergy and waste, MILTON OF CRAIGIE GRID primaryConnected9.499 MW
  • BALDOVIE WASTE TO ENERGY PLANTMVV ENVIRONMENT BALDOVIE LIMITED, Bioenergy and waste, MILTON OF CRAIGIE GRID primaryConnected8.265 MW
  • BALDOVIE ROADMICHELIN SCOTLAND INNOVATION PARC LTD, Wind, BALDOVIE primaryConnected4.21 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?