QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / SSEN / Grid supply point

WILLOWDALE

Grid supply point in North of Scotland (SHEPD)

SSEN Embedded Capacity Register, September 2026 edition

1site of 1 MW and over
2 MWcapacity
–connected (0 sites)
2 MWaccepted to connect (1 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage12 MW–2 MW

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated1–2 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

August 2026 edition to September 2026 edition: 1 site matched. Every August site and every September site at this grid supply point had a match in the other edition.

No change to the status, capacity, technology or customer of the sites here in the editions of SSEN's register QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.