QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Neepsend Energy Park

Neepsend Energy Park at Neepsend

Northern Powergrid Embedded Capacity Register 1MW and Over, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Customer
Neepsend Energy Park
Site name
Neepsend Energy Park
Address
Land, Club Mill Road Road, Sheffield, South Yorkshire, S6 2BL
Grid reference
Easting 433900, northing 389893
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
Neepsend
Bulk supply point
Neepsend
Primary substation
Neepsend Energy Park
Connection voltage
33 kV
Technology group
Storage
Energy source 1
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 45 MW registered
Registered capacity
45 MW
Change to maximum export capacity
45 MW
Change to maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
15 Sep 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
12 Oct 2023
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Neepsend

GSP view

2 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 52.1 MW: 7.1 MW connected, 45 MW accepted to connect.

  • Parkwood LandfillParkwood Landfill, Bioenergy and waste, Penistone Road primaryConnected5 MW
  • Fletchers Bakery HybridFletchers Bakery Hybrid, Gas and other fossil, Claywheels Lane primaryConnected2.05 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose