WHITBROOK POWER
AMP ENERGY SERVICES LTD at WHITEGATE GSP
ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Date connected
- 22 Sep 2023
- Status
- Connected
- Customer
- AMP ENERGY SERVICES LTD
- Site name
- WHITBROOK POWER
- Address
- LAND TO THE WEST SIDE OF HANSON STREET, MIDDLETON, MANCHESTER, GREATER MANCHESTER, M24 6AG
- Grid reference
- Easting 387378, northing 406104
- Licence area
- North West England (ENWL)
- Grid supply point
- WHITEGATE GSP
- Bulk supply point
- CHADDERTON
- Primary substation
- TOWNLEY ST
- Connection voltage
- 11 kV
- Technology group
- Gas and other fossil
- Energy source 1
- FOSSIL - GAS, ENGINE (COMBUSTION / RECIPROCATING): 5.07 MW registered
- Registered capacity
- 5.07 MW
- Maximum export capacity
- 5.07 MW
- Maximum import capacity
- 0.2 MW
- Change to maximum import capacity
- 0 MW
- Flexible connection
- No
- In a connection queue
- Not stated
- Date accepted
- Not stated
- Target energisation date
- Not stated
- Distribution reinforcement reference
- Not published by ENWL
- Transmission reinforcement reference
- Not stated
- Export MPAN
- 1650000268165
- Import MPAN
- 1650000268156
- Last updated
- 14 Mar 2024
- Tracked since
- May 2026 edition
Change history
Tracked since the May 2026 edition, across 2 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at WHITEGATE GSP
GSP view23 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 359 MW: 79 MW connected, 280 MW accepted to connect.
- BROADGATE CHADDERTON GENERATIONCHADDERTON GENERATION LIMITED, Gas and other fossilConnected21.052 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose