HYNDBURN WIND FARM

ENERGIEKONTOR UK HY GMBH & CO. WP HYNDBU at PENWORTHAM EAST GSP / ROCHDALE SGT 1 GROUP

ENWL Embedded Capacity Register 2 – 1MW and above, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
1 Apr 2013
Status
Connected
Planning consent
Granted 17 Oct 2010
Hyndburn, reference 11/09/0512 · Source: REPD
Customer
ENERGIEKONTOR UK HY GMBH & CO. WP HYNDBU
Site name
HYNDBURN WIND FARM
Address
HASLINGDEN OLD ROAD, HASLINGDEN OLD ROAD, ACCRINGTON, LANCASHIRE, BB5 3RT
Grid reference
Easting 374590, northing 425063
Licence area
North West England (ENWL)
Grid supply point
PENWORTHAM EAST GSP / ROCHDALE SGT 1 GROUP
Bulk supply point
BLACKBURN
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 25.102 MW registered
Registered capacity
25.102 MW
Maximum export capacity
23.847 MW
Maximum import capacity
0.389 MW
Change to maximum import capacity
0 MW
Flexible connection
No
In a connection queue
Not stated
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by ENWL
Transmission reinforcement reference
Not stated
Export MPAN
1640000177316
Import MPAN
1640000177307
Last updated
6 Dec 2021
Tracked since
May 2026 edition

Change history

Tracked since the May 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at PENWORTHAM EAST GSP / ROCHDALE SGT 1 GROUP

GSP view

30 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 460 MW: 317 MW connected, 143 MW accepted to connect.

See all 30

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.