QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / ENWL / Grid supply point

ROCHDALE SGTS 2 3 4

Grid supply point in North West England (ENWL)

ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition

25sites of 1 MW and over
466 MWcapacity
180 MWconnected (13 sites)
286 MWaccepted to connect (12 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage6253 MW18 MW235 MW
Wind4126 MW118 MW8 MW
Gas and other fossil762.2 MW32.2 MW30 MW
Solar520.3 MW6.6 MW13.7 MW
Bioenergy and waste34.6 MW4.6 MW–

Storage capacity in MWh: not published by ENWL.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
CASTLETON1–5 MW
CASTLETON1–4.2 MW
CASTLETON1–4 MW
CASTLETON422.5 MW56.1 MW
PRIVATE SUBSTATION165 MW–
BURNLEY26 MW20 MW
BURNLEY324.1 MW–
BURNLEY1–7.9 MW
BELFIELD34.1 MW1.1 MW
BELFIELD12.5 MW–
BELFIELD136.3 MW–
BELLFIELD1–30 MW
ROCHDALE CENTRAL12.1 MW–
Not stated417 MW158 MW

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

May 2026 edition to September 2026 edition: 25 sites matched. Every May site and every September site at this grid supply point had a match in the other edition.

No change to the status, capacity, technology or customer of the sites here in the editions of ENWL's register QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.