Naturalis Energy Developments

Customer named in the DNOs’ registers

In SPEN’s September 2026 edition

The registers spell this customer’s name more than one way: “Naturalis Energy Developments” (1 site) and “Naturalis Energy Developments Ltd” (1 site).

2sites of 1 MW and over
138 MWcapacity
–connected (0 sites)
138 MWaccepted to connect (2 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
SPENSeptember 2026 edition2138 MW–138 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage2138 MW–138 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Knockippen Energy ParkSPENAyrStorageAccepted to connect90.3
St Marys Isle Solar FarmSPENTonglandStorageAccepted to connect48

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
AyrSPEN1–90.3 MW
TonglandSPEN1–48 MW

What changed recently

Changes to its sites found in both editions of each pair, newest first.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 2 sites matched. Every August site and every September site had a match in the other edition.

  • St Marys Isle Solar FarmSPEN, August 2026 editionTarget energisation date moved from 27 Jan 2030 to 27 Jun 2030 (5 months later)
  • St Marys Isle Solar FarmSPEN, May 2026 editionTarget energisation date moved from 27 Feb 2030 to 27 Jan 2030 (1 month earlier)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?