QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

BRITISH TELECOMMUNICATIONS PLC

Customer named in the DNOs’ registers

In ENWL’s October 2026 edition

3sites of 1 MW and over
7.7 MWcapacity
7.7 MWconnected (3 sites)
–accepted to connect (0 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
ENWLOctober 2026 edition37.7 MW7.7 MW–

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil37.7 MW7.7 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
DIAL HOUSEENWLKEARSLEY 132 GSPGas and other fossilConnected4.14
PITT STREETENWLROCHDALE SGTS 2 3 4Gas and other fossilConnected2.5
TURRET HOUSE ATEENWLKEARSLEY 132 GSPGas and other fossilConnected1.035

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
KEARSLEY 132 GSPENWL25.2 MW–
ROCHDALE SGTS 2 3 4ENWL12.5 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 3 sites matched. Every September site and every October site had a match in the other edition.

No change to any detail QueueWatch tracks for its sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?