- Connection date
- 30 Apr 2029
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 20 Dec 2019
Scottish Government (S36), reference ECU00000673 · Source: REPD - Technology
- Substation + Onshore wind
- Total capacity
- 96 MW
- Connected now
- 0 MW
- Still to connect
- 96 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001408
- In the register since
- February 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Nov 2025 registerConnection date moved from 31 Oct 2026 to 30 Apr 2029 (+30 months)
- 27 Jun 2025 registerTechnology changed from Onshore wind to Onshore wind, Substation
- 26 Feb 2021 registerAdded to the register
Also at Tangy IV 132KV Substation
Substation viewNo other projects in the register at this connection point.