PERIGUS ENERGY UK LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Kennoxhead Wind Farm | Coalburn 132kV | Onshore wind | 112 | 28 Apr 2028 | Not stated | Consents Approved |
| Woodcock Hill Wind Farm | Woodcock Hill WF Substation | Storage with solar or wind | 90 | 31 Oct 2032 | Gate 1 | Scoping |
| Knockton Wind Farm | Alyth 400kV Substation | Onshore wind | 130 | 31 Oct 2033 | Not stated | Scoping |
| Seat Hill Wind Farm | Seat Hill 132kV Substation | Storage with solar or wind | 90 | 30 Oct 2035 | Gate 1 | Scoping |
| Dunan Hill | Dunan Hill 400kV substation | Storage with solar or wind | 250 | 31 Oct 2035 −12 mo | Gate 1 | Scoping |
| Scaw Law Wind Farm | Scaw Law 132kV substation | Storage with solar or wind | 60 | 31 Oct 2036 | Not stated | Scoping |
Recent changes
- Dunan HillNorth Scotland, Storage with solar or windConnection date moved from 1 Nov 2036 to 31 Oct 2035 (−12 months)−12 mo
- Seat Hill Wind FarmSouth Scotland, Storage with solar or windConnection date moved from 31 Jul 2032 to 30 Oct 2035 (+39 months)+39 mo
- Dunan HillNorth Scotland, Storage with solar or windConnection date moved from 11 Nov 2036 to 1 Nov 2036 (10 days earlier)
- Dunan HillNorth Scotland, Storage with solar or windMarked as Gate 1
- Seat Hill Wind FarmSouth Scotland, Storage with solar or windConnection date moved from 30 Oct 2035 to 31 Jul 2032 (−39 months)−39 mo
- Seat Hill Wind FarmSouth Scotland, Storage with solar or windMarked as Gate 1
- Dunan HillNorth Scotland, Storage with solar or windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Kennoxhead Wind FarmSouth Scotland, Onshore windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Knockton Wind FarmNorth Scotland, Onshore windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Scaw Law Wind FarmSouth Scotland, Storage with solar or windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Seat Hill Wind FarmSouth Scotland, Storage with solar or windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Woodcock Hill Wind FarmNorth Scotland, Storage with solar or windCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- Woodcock Hill Wind FarmNorth Scotland, Storage with solar or windMarked as Gate 1
- Kennoxhead Wind FarmSouth Scotland, Onshore windConnection point changed from Kennoxhead GSP to Coalburn 132kV
- Kennoxhead Wind FarmSouth Scotland, Onshore windConnection date moved from 1 Apr 2028 to 28 Apr 2028 (+1 month)+1 mo
- Seat Hill Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
- Knockton Wind FarmNorth Scotland, Onshore windConnection point changed from Knockton Wind Farm 132kV Substation to Alyth 400kV Substation
- Dunan HillNorth Scotland, Storage with solar or windAdded to the registerNew
- Scaw Law Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
- Woodcock Hill Wind FarmNorth Scotland, Storage with solar or windAdded to the registerNew
- Kennoxhead Wind FarmSouth Scotland, Onshore windConnection date moved from 27 Feb 2024 to 1 Apr 2028 (+49 months)+49 mo
- Knockton Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Kennoxhead Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Kennoxhead to Kennoxhead GSP)
- Kennoxhead Wind FarmSouth Scotland, Onshore windCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to ORSTED ONSHORE UK LIMITED
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?