Dunan Hill
- Connection date
- 31 Oct 2035 −12 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004433
- In the register since
- June 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 1 Nov 2036 to 31 Oct 2035 (−12 months)
- 10 Oct 2026 registerConnection date moved from 11 Nov 2036 to 1 Nov 2036 (10 days earlier)
- 10 Oct 2026 registerMarked as Gate 1
- 8 May 2026 registerCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- 28 Jun 2024 registerAdded to the register
Also at Dunan Hill 400kV substation
Substation viewNo other projects in the register at this connection point.