Kennoxhead Wind Farm
- Connection date
- 28 Apr 2028
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 112 MW
- Connected now
- 0 MW
- Still to connect
- 112 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000319
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 8 May 2026 registerCustomer changed from ORSTED ONSHORE UK LIMITED to PERIGUS ENERGY UK LIMITED
- 19 Dec 2025 registerConnection point changed from Kennoxhead GSP to Coalburn 132kV
- 21 Nov 2025 registerConnection date moved from 1 Apr 2028 to 28 Apr 2028 (+1 month)
- 26 Apr 2024 registerConnection date moved from 27 Feb 2024 to 1 Apr 2028 (+49 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Kennoxhead to Kennoxhead GSP)
- 31 Aug 2021 registerCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to ORSTED ONSHORE UK LIMITED
Also at Coalburn 132kV
Substation viewNo other projects in the register at this connection point.