Norfolk Vanguard East Ltd
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Vanguard East | Necton 400kV Substation | Offshore wind | 1,320 | 1 Apr 2028 | Gate 2 | Consents Approved |
Recent changes
- Vanguard EastEngland and Wales, Offshore windConnection point changed from Vanguard East 275/66kV Offshore Substation to Necton 400kV Substation
- Vanguard EastEngland and Wales, Offshore windStage 1: Status changed from Scoping to Consents Approved
- Vanguard EastEngland and Wales, Offshore windStage 1: Given a Gate 2 connection offerGate 2
- Vanguard EastEngland and Wales, Offshore windStage 2: Status changed from Scoping to Consents Approved
- Vanguard EastEngland and Wales, Offshore windStage 2: Given a Gate 2 connection offerGate 2
- Vanguard EastEngland and Wales, Offshore windConnection point changed from Necton 400kV Substation to Vanguard East 275/66kV Offshore Substation
- Vanguard EastEngland and Wales, Offshore windStage 1: Connection date moved from 31 Dec 2027 to 1 Apr 2028 (+3 months)+3 mo
- Vanguard EastEngland and Wales, Offshore windStage 1: Gate marking removed (was Gate 2)
- Vanguard EastEngland and Wales, Offshore windStage 2: Gate marking removed (was Gate 2)
- Vanguard EastEngland and Wales, Offshore windConnection point changed from Vanguard East 275/66kV Offshore Substation to Necton 400kV Substation
- Vanguard EastEngland and Wales, Offshore windStage 1: Connection date moved from 1 Apr 2028 to 31 Dec 2027 (−3 months)−3 mo
- Vanguard EastEngland and Wales, Offshore windStage 1: Given a Gate 2 connection offerGate 2
- Vanguard EastEngland and Wales, Offshore windStage 2: Given a Gate 2 connection offerGate 2
- Vanguard EastEngland and Wales, Offshore windConnection point changed from Necton 400kV Substation to Vanguard East 275/66kV Offshore Substation
- Vanguard EastEngland and Wales, Offshore windStage 1: Connection date moved from 20 Mar 2028 to 1 Apr 2028 (12 days later)
- Vanguard EastEngland and Wales, Offshore windStage 1: Capacity changed from 960 MW to 400 MW
- Vanguard EastEngland and Wales, Offshore windStage 1: Connection date moved from 1 Mar 2027 to 20 Mar 2028 (+13 months)+13 mo
- Vanguard EastEngland and Wales, Offshore windStage 2: Capacity changed from 360 MW to 920 MW
- Vanguard EastEngland and Wales, Offshore windConnection point changed from Vanguard East Offshore Substation to Necton 400kV Substation
- Vanguard EastEngland and Wales, Offshore windRestructured from 1 stage (1,200 MW from 1 Apr 2025) to 2 stages (960 MW from 1 Mar 2027, 360 MW from 31 Dec 2028). First connection date +23 months+23 mo
- Vanguard EastEngland and Wales, Offshore windConnection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?