Mona Offshore Wind Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Mona Offshore Wind Farm | Bodelwyddan 400kV Substation | Offshore wind | 1,500 | 31 Oct 2029 | Not stated | Scoping |
Recent changes
- Mona Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Wylfa 400kV Substation to Bodelwyddan 400kV Substation
- Mona Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 31 Oct 2029 (−41 months)−41 mo
- Mona Offshore Wind FarmEngland and Wales, Offshore windRenamed from Project Elizabeth (Yellow)
- Mona Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from BP ALTERNATIVE ENERGY INVESTMENTS LIMITED to Mona Offshore Wind Limited
- Mona Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- Mona Offshore Wind FarmEngland and Wales, Offshore windRenamed from Project Elizabeth
- Mona Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Yellow Offshore Substation to Wylfa 400kV
- Mona Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 4 Jan 2033 to 1 Apr 2033 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?