Juniper Energy Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Iver | Iver 275kV Substation | Storage | 49.9 | 29 Oct 2027 | Gate 1 | Scoping |
| Laleham | Laleham 132kV Substation | Storage | 90 | 30 May 2028 | Gate 1 | Scoping |
Recent changes
- IverEngland and Wales, StorageMarked as Gate 1
- LalehamEngland and Wales, StorageStage 2: Marked as Gate 1
- LalehamEngland and Wales, StorageStage 1: Marked as Gate 1
- LalehamEngland and Wales, StorageStage 1: Technology changed from Storage to Demand, Storage
- LalehamEngland and Wales, StorageStage 2: Technology changed from Storage to Demand, Storage
- LalehamEngland and Wales, StorageRestructured from 1 stage (49.9 MW from 1 Nov 2025) to 2 stages (49.9 MW from 30 May 2028, 40.1 MW from 31 Oct 2030). First connection date +31 months+31 mo
- LalehamEngland and Wales, StorageCustomer changed from PIVOTED POWER LLP to Juniper Energy Limited
- IverEngland and Wales, StorageCustomer changed from PIVOTED POWER LLP to Juniper Energy Limited
- IverEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 29 Oct 2027 (+48 months)+48 mo
- LalehamEngland and Wales, StorageConnection date moved from 31 Oct 2024 to 1 Nov 2025 (+12 months)+12 mo
- IverEngland and Wales, StorageSubstation name updated in the register (from Iver 275kV to Iver 275kV Substation)
- LalehamEngland and Wales, StorageSubstation name updated in the register (from Laleham 275kV to Laleham 275kV Substation)
- LalehamEngland and Wales, StorageConnection date moved from 31 Oct 2022 to 31 Oct 2024 (+24 months)+24 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?