Projects / England and Wales
- Connection date
- 30 May 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage
- Total capacity
- 90 MW
- Connected now
- 0 MW
- Still to connect
- 90 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001063
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 30 May 2028 | Gate 1 | Scoping |
| 2 | 0 | 40.1 | 90 | 31 Oct 2030 | Gate 1 | Scoping |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Laleham 132kV Substation
Substation viewNo other projects in the register at this connection point.