- Connection date
- 30 May 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage
- Total capacity
- 90 MW
- Connected now
- 0 MW
- Still to connect
- 90 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001063
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 30 May 2028 | Gate 1 | Scoping |
| 2 | 0 | 40.1 | 90 | 31 Oct 2030 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Jul 2026 registerStage 2: Marked as Gate 1
- 26 Jun 2026 registerStage 1: Marked as Gate 1
- 29 Aug 2025 registerStage 1: Technology changed from Storage to Demand, Storage
- 29 Aug 2025 registerStage 2: Technology changed from Storage to Demand, Storage
- 27 Jun 2025 registerRestructured from 1 stage (49.9 MW from 1 Nov 2025) to 2 stages (49.9 MW from 30 May 2028, 40.1 MW from 31 Oct 2030). First connection date +31 months
- 31 Jan 2025 registerCustomer changed from PIVOTED POWER LLP to Juniper Energy Limited
- 30 Jan 2024 registerConnection date moved from 31 Oct 2024 to 1 Nov 2025 (+12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Laleham 275kV to Laleham 275kV Substation)
- 25 Feb 2022 registerConnection date moved from 31 Oct 2022 to 31 Oct 2024 (+24 months)
Also at Laleham 132kV Substation
Substation viewNo other projects in the register at this connection point.