- Connection date
- 29 Oct 2027
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001141
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerMarked as Gate 1
- 24 Dec 2024 registerCustomer changed from PIVOTED POWER LLP to Juniper Energy Limited
- 26 Apr 2024 registerConnection date moved from 31 Oct 2023 to 29 Oct 2027 (+48 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Iver 275kV to Iver 275kV Substation)
Also at Iver 275kV Substation
Substation viewNo other projects in the register at this connection point.