Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

FRED OLSEN RENEWABLES LIMITED

Customer named in the TEC register

7projects in the register
470 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Windy Standard 1 RepowerDun Hill 132/33kVOnshore wind21.930 Jun 2031Not statedScoping
Scawd Law Wind FarmGala North 400/132kV SubstationStorage with solar or wind6430 Apr 2032Gate 1Scoping
Balnespick Wind FarmBalnespick Wind Farm 132kV/33kV SubstationStorage with solar or wind5831 Oct 2032Not statedScoping
Lees Hill Renewable Energy ParkKelloe Mains 400kV SubstationStorage with solar or wind5415 Apr 2033Not statedScoping
Lethen Wind FarmLethen Wind Farm 132/33kV SubstationOnshore wind1141 Dec 2033 −1 moGate 1Scoping
Balgray Wind FarmDumfries North 400/132kV substationStorage with solar or wind43.231 Oct 2037Gate 1Scoping
Culachy Wind FarmFort Augustus 2 400kV SubstationStorage with solar or wind11531 Oct 2037Gate 1Scoping

Recent changes

  • Lethen Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Dec 2033 to 1 Dec 2033 (−1 month)−1 mo
  • Balnespick Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Tomatin 275/132 kV Substation to Balnespick Wind Farm 132kV/33kV Substation
  • Scawd Law Wind FarmSouth Scotland, Storage with solar or windMarked as Gate 1
  • Lethen Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • Balgray Wind FarmEngland and Wales, Storage with solar or windConnection point changed from Gretna 400/132kV to Dumfries North 400/132kV substation
  • Balgray Wind FarmEngland and Wales, Storage with solar or windTransmission owner changed from SPT to NGET
  • Balgray Wind FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Culachy Wind FarmNorth Scotland, Storage with solar or windMarked as Gate 1
  • Balgray Wind FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Culachy Wind FarmNorth Scotland, Storage with solar or windConnection point changed from Fort Augustus 400kV to Fort Augustus 2 400kV Substation
  • Balnespick Wind FarmNorth Scotland, Storage with solar or windAdded to the registerNew
  • Culachy Wind FarmNorth Scotland, Storage with solar or windAdded to the registerNew
  • Lees Hill Renewable Energy ParkSouth Scotland, Storage with solar or windAdded to the registerNew
  • Windy Standard 1 RepowerSouth Scotland, Onshore windAdded to the registerNew
  • Lethen Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Oct 2029 to 31 Dec 2033 (+50 months)+50 mo
  • Lethen Wind FarmNorth Scotland, Onshore windTechnology changed from Storage, Onshore wind to Onshore wind
  • Scawd Law Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
  • Lethen Wind FarmNorth Scotland, Onshore windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO