Lethen Wind Farm
FRED OLSEN RENEWABLES LIMITED at Lethen Wind Farm 132/33kV Substation
- Connection date
- 1 Dec 2033 −1 month since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 114 MW
- Connected now
- 0 MW
- Still to connect
- 114 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002307
- In the register since
- January 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Dec 2033 to 1 Dec 2033 (−1 month)
- 12 May 2026 registerMarked as Gate 1
- 30 May 2025 registerConnection date moved from 31 Oct 2029 to 31 Dec 2033 (+50 months)
- 30 May 2025 registerTechnology changed from Storage, Onshore wind to Onshore wind
- 31 Jan 2023 registerAdded to the register
Also at Lethen Wind Farm 132/33kV Substation
Substation viewNo other projects in the register at this connection point.