Scawd Law Wind Farm
FRED OLSEN RENEWABLES LIMITED at Gala North 400/132kV Substation
- Connection date
- 30 Apr 2032
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 64 MW
- Connected now
- 0 MW
- Still to connect
- 64 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-005865
- In the register since
- May 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 May 2026 registerMarked as Gate 1
- 30 May 2025 registerAdded to the register
Also at Gala North 400/132kV Substation
Substation view2 other projects, 314 MW still to connect at this substation in total. 150 MW is due to connect here before this project’s connection date of 30 Apr 2032.