ESB ASSET DEVELOPMENT UK LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| West Torrisdale | Carradale 2 132/33kV GSP Substation | Onshore wind | 50 | 31 May 2028 | Not stated | Scoping |
| Chleansaid Wind Farm | Chleansaid Wind Farm 132kV Substation | Onshore wind | 96 | 10 Sep 2028 +13 mo | Gate 2 | Consents Approved |
| Millmoor Rig Wind Farm | Hawick GSP | Onshore wind | 92.8 | 30 Oct 2029 | Not stated | Scoping |
| Craigneil Wind Farm | Fetteresso 132/33kV GSP Substation | Onshore wind | 42 | 31 Oct 2030 | Not stated | Scoping |
| Celtic Sea Offshore Wind Farm (ESB) | CELTIC SEA 275/66KV OFFSHORE SUBSTATION | Offshore wind | 1,000 | 31 Oct 2031 | Gate 1 | Scoping |
Left the register since January 2021: CPG Power (49.9 MW), ESB Blackhillock Synchronous Compensation (0 MW), Hunterston Synchronous Compensation (0 MW), Spittal Synchronous Compensation (0 MW).
Recent changes
- Chleansaid Wind FarmNorth Scotland, Onshore windStatus changed from Scoping to Consents Approved
- West TorrisdaleNorth Scotland, Onshore windConnection point changed from Carradale 1 GSP to Carradale 2 132/33kV GSP Substation
- Craigneil Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Fetteresso GSP to Fetteresso 132/33kV GSP Substation)
- Chleansaid Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Jul 2027 to 10 Sep 2028 (+13 months)+13 mo
- Chleansaid Wind FarmNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Celtic Sea Offshore Wind Farm (ESB)England and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to CELTIC SEA 275/66KV OFFSHORE SUBSTATION
- Celtic Sea Offshore Wind Farm (ESB)England and Wales, Offshore windMarked as Gate 1
- Craigneil Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- West TorrisdaleNorth Scotland, Onshore windConnection date moved from 30 Apr 2027 to 31 May 2028 (+13 months)+13 mo
- CPG PowerEngland and Wales, Thermal (gas, biomass, waste)Left the register (49.9 MW from 30 Jun 2026)49.9 MW
- Millmoor Rig Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Hawick 132/33kV to Hawick GSP)
- Millmoor Rig Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Hawick GSP to Hawick 132/33kV)
- Chleansaid Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Chleansaid Wind Farm 132kV to Chleansaid Wind Farm 132kV Substation)
- West TorrisdaleNorth Scotland, Onshore windConnection point changed from Carradale GSP to Carradale 1 GSP
- Millmoor Rig Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Hawick to Hawick GSP)
- CPG PowerEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Carrington 400kV to Carrington 400KV Substation)
- Celtic Sea Offshore Wind Farm (ESB)England and Wales, Offshore windAdded to the registerNew
- West TorrisdaleNorth Scotland, Onshore windConnection date moved from 31 Oct 2026 to 30 Apr 2027 (+6 months)+6 mo
- Millmoor Rig Wind FarmSouth Scotland, Onshore windAdded to the registerNew
- Spittal Synchronous CompensationNorth Scotland, OtherLeft the register (0 MW from 30 Oct 2023)0 MW
- ESB Blackhillock Synchronous CompensationNorth Scotland, OtherLeft the register (0 MW from 31 Oct 2023)0 MW
- Hunterston Synchronous CompensationSouth Scotland, OtherLeft the register (0 MW from 30 Oct 2024)0 MW
- ESB Blackhillock Synchronous CompensationNorth Scotland, OtherAdded to the registerNew
- Hunterston Synchronous CompensationSouth Scotland, OtherAdded to the registerNew
- Spittal Synchronous CompensationNorth Scotland, OtherAdded to the registerNew
- Chleansaid Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- West TorrisdaleNorth Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose