West Torrisdale
ESB ASSET DEVELOPMENT UK LIMITED at Carradale 2 132/33kV GSP Substation
- Connection date
- 31 May 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000944
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerConnection point changed from Carradale 1 GSP to Carradale 2 132/33kV GSP Substation
- 28 Feb 2025 registerConnection date moved from 30 Apr 2027 to 31 May 2028 (+13 months)
- 31 Jan 2023 registerConnection point changed from Carradale GSP to Carradale 1 GSP
- 29 Jul 2022 registerConnection date moved from 31 Oct 2026 to 30 Apr 2027 (+6 months)
- 30 Mar 2021 registerSubstation name updated in the register (from Carradale to Carradale GSP)
Also at Carradale 2 132/33kV GSP Substation
Substation viewNo other projects in the register at this connection point.