Celtic Sea Offshore Wind Farm (ESB)
ESB ASSET DEVELOPMENT UK LIMITED at CELTIC SEA 275/66KV OFFSHORE SUBSTATION
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002219
- In the register since
- November 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 8 May 2026 registerConnection point changed from Alverdiscott 400kV Substation to CELTIC SEA 275/66KV OFFSHORE SUBSTATION
- 8 May 2026 registerMarked as Gate 1
- 29 Nov 2022 registerAdded to the register
Also at CELTIC SEA 275/66KV OFFSHORE SUBSTATION
Substation viewNo other projects in the register at this connection point.