BROCKWELL ENERGY LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Breezy Hill Wind Farm | New Cumnock A 132kV | Onshore wind | 80 | 30 Apr 2028 | Not stated | Scoping |
| Glentaggart 150MW BESS | GLENTAGGART 150MW BESS 132kV SUBSTATION | Storage | 150 | 30 Oct 2030 | Gate 1 | Scoping |
| Westfield BESS | Westfield 400kV Substation | Storage | 350 | 31 Oct 2031 | Gate 1 | Scoping |
| Glenmuir Windfarm | Glenmuir Windfarm 132kV Substation | Onshore wind | 80 | 30 Jun 2036 | Gate 1 | Scoping |
| Upper Beoch Windfarm | New Cumnock North 132kV Substation | Onshore wind | 80 | 31 Jul 2036 +33 mo | Gate 1 | Scoping |
| Chalmerston Windfarm | CHALMERSTON WINDFARM 132kV SUBSTATION | Onshore wind | 75 | 31 Oct 2037 +48 mo | Gate 1 | Scoping |
Recent changes
- Chalmerston WindfarmSouth Scotland, Onshore windConnection date moved from 31 Oct 2033 to 31 Oct 2037 (+48 months)+48 mo
- Upper Beoch WindfarmSouth Scotland, Onshore windConnection date moved from 31 Oct 2033 to 31 Jul 2036 (+33 months)+33 mo
- Chalmerston WindfarmSouth Scotland, Onshore windConnection point changed from New Cumnock 275/132kV Substation to CHALMERSTON WINDFARM 132kV SUBSTATION
- Glentaggart 150MW BESSSouth Scotland, StorageConnection point changed from Redshaw 400kV to GLENTAGGART 150MW BESS 132kV SUBSTATION
- Chalmerston WindfarmSouth Scotland, Onshore windMarked as Gate 1
- Glenmuir WindfarmSouth Scotland, Onshore windMarked as Gate 1
- Glentaggart 150MW BESSSouth Scotland, StorageMarked as Gate 1
- Upper Beoch WindfarmSouth Scotland, Onshore windMarked as Gate 1
- Westfield BESSSouth Scotland, StorageConnection point changed from Westfield 275/132kV to Westfield 400kV Substation
- Westfield BESSSouth Scotland, StorageMarked as Gate 1
- Breezy Hill Wind FarmSouth Scotland, Onshore windConnection point changed from New Cumnock 275/132kV to New Cumnock A 132kV
- Upper Beoch WindfarmSouth Scotland, Onshore windConnection point changed from New Cumnock 275/132kV Substation to New Cumnock North 132kV Substation
- Westfield BESSSouth Scotland, StorageConnection point changed from Westfield 275/132/33kV to Westfield 275/132kV
- Breezy Hill Wind FarmSouth Scotland, Onshore windConnection point changed from New Cumnock 132kV Substation to New Cumnock 275/132kV
- Glentaggart 150MW BESSSouth Scotland, StorageSubstation name updated in the register (from Redshaw 400KV Substation to Redshaw 400kV)
- Westfield BESSSouth Scotland, StorageConnection point changed from Westfield 275kV Substation to Westfield 275/132/33kV
- Glenmuir WindfarmSouth Scotland, Onshore windAdded to the registerNew
- Glentaggart 150MW BESSSouth Scotland, StorageAdded to the registerNew
- Westfield BESSSouth Scotland, StorageAdded to the registerNew
- Upper Beoch WindfarmSouth Scotland, Onshore windAdded to the registerNew
- Chalmerston WindfarmSouth Scotland, Onshore windAdded to the registerNew
- Breezy Hill Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from New Cumnock 132kV to New Cumnock 132kV Substation)
- Breezy Hill Wind FarmSouth Scotland, Onshore windConnection date moved from 31 Oct 2027 to 30 Apr 2028 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?