Westfield BESS
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 350 MW
- Connected now
- 0 MW
- Still to connect
- 350 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004210
- In the register since
- May 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Mar 2026 registerConnection point changed from Westfield 275/132kV to Westfield 400kV Substation
- 31 Mar 2026 registerMarked as Gate 1
- 29 Oct 2024 registerConnection point changed from Westfield 275/132/33kV to Westfield 275/132kV
- 27 Sep 2024 registerConnection point changed from Westfield 275kV Substation to Westfield 275/132/33kV
- 31 May 2024 registerAdded to the register
Also at Westfield 400kV Substation
Substation viewNo other projects in the register at this connection point.