Chalmerston Windfarm
BROCKWELL ENERGY LIMITED at CHALMERSTON WINDFARM 132kV SUBSTATION
- Connection date
- 31 Oct 2037 +48 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 75 MW
- Connected now
- 0 MW
- Still to connect
- 75 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004057
- In the register since
- February 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2033 to 31 Oct 2037 (+48 months)
- 14 Jul 2026 registerConnection point changed from New Cumnock 275/132kV Substation to CHALMERSTON WINDFARM 132kV SUBSTATION
- 15 May 2026 registerMarked as Gate 1
- 27 Feb 2024 registerAdded to the register
Also at CHALMERSTON WINDFARM 132kV SUBSTATION
Substation viewNo other projects in the register at this connection point.