Edinbane Windfarm
- Connection date
- 30 Apr 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 90 MW
- Connected now
- 41.4 MW
- Still to connect
- 48.6 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000135
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 41.4 | 0 | 41.4 | None | Not stated | Built |
| 2 | 0 | 48.6 | 90 | 30 Apr 2033 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerStage 1: Gate marking removed (was Gate 1)
- 10 Oct 2026 registerStage 1: Marked as Gate 1
- 10 Oct 2026 registerStage 2: Marked as Gate 1
- 24 Dec 2024 registerSubstation name updated in the register (from Edinbane GSP to Edinbane 132/33kV Substation)
- 24 Dec 2024 registerStage 2: Connection date moved from 1 Jan 2030 to 30 Apr 2033 (+40 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Edinbane to Edinbane GSP)
- 29 Jul 2022 registerNew stage added (48.6 MW from 1 Jan 2030)
- 29 Apr 2022 registerRenamed from Edinbane Wind - Skye
- 29 Apr 2022 registerTechnology changed from Onshore wind to Storage, Onshore wind
Also at Edinbane 132/33kV Substation
Substation view1 other project, 88.2 MW still to connect at this substation in total.