Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Creag Riabhach Wind Farm

CREAG RIABHACH WIND FARM LTD at Creag Riabhach 132/33kV Substation

Connection date
31 Jul 2027
Gate
Gate 1
Status
Scoping
Planning consent
Granted 17 Oct 2016
Scottish Government (S36), reference EC00002078 · Source: REPD
Technology
Onshore wind
Total capacity
105 MW
Connected now
92.4 MW
Still to connect
12.6 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-000109
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
192.4092.4NoneNot statedBuilt
2012.610531 Jul 2027Gate 1Scoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 22 Oct 2026 register
    Stage 2: Status changed from Consents Approved to Scoping
  • 22 Oct 2026 register
    Stage 2: Marked as Gate 1
  • 30 Jan 2024 register
    New stage added (12.6 MW from 31 Jul 2027)
  • 31 Mar 2023 register
    92.4 MW now connected
  • 31 Mar 2023 register
    Status changed from Consents Approved to Built
  • 29 Apr 2022 register
    Connection date moved from 5 Jul 2022 to 25 Oct 2022 (+4 months)
  • 26 Feb 2021 register
    Connection date moved from 7 May 2022 to 5 Jul 2022 (+2 months)

Also at Creag Riabhach 132/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.