West Burton 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| West Burton | ENSO GREEN HOLDINGS A LIMITED | Storage with solar or wind | 120 | 30 Jun 2027 | Gate 2 | Under Construction/Commissioning |
Recent changes
- West BurtonEngland and Wales, Storage with solar or windStatus changed from Scoping to Under Construction/Commissioning
- West BurtonEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- West BurtonEngland and Wales, Storage with solar or windRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (120 MW from 30 Jun 2027). First connection date +24 months+24 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?