West Burton
ENSO GREEN HOLDINGS A LIMITED at West Burton 132kV Substation
- Connection date
- 30 Jun 2027
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage + Solar
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001323
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 7 Jul 2026 registerGiven a Gate 2 connection offer
- 29 Oct 2024 registerRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (120 MW from 30 Jun 2027). First connection date +24 months
Also at West Burton 132kV Substation
Substation viewNo other projects in the register at this connection point.