Uskmouth 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Uskmouth - New Connection | AW1 ENERGY STORAGE LIMITED | Storage | 120 | 31 Oct 2026 Past date | Gate 2 | Under Construction/Commissioning |
| Solutia | UK POWER RESERVE LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
| Uskmouth | USKMOUTH ENERGY STORAGE LIMITED | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Uskmouth - New ConnectionEngland and Wales, StorageConnection date moved from 31 Oct 2027 to 31 Oct 2026 (−12 months)−12 mo
- Uskmouth - New ConnectionEngland and Wales, StorageConnection date moved from 31 Oct 2026 to 31 Oct 2027 (+12 months)+12 mo
- Uskmouth - New ConnectionEngland and Wales, StorageStatus changed from Scoping to Under Construction/Commissioning
- Uskmouth - New ConnectionEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- UskmouthEngland and Wales, Storage350 MW now connectedConnected
- UskmouthEngland and Wales, StorageStatus changed from Under Construction/Commissioning to Built
- UskmouthEngland and Wales, StorageRestructured from 2 stages (230 MW from 30 Jun 2024, 120 MW from 30 Oct 2038) to 1 stage (350 MW from 31 Mar 2025). First connection date +9 months+9 mo
- Uskmouth - New ConnectionEngland and Wales, StorageConnection point changed from Uskmouth 275kV Substation to Uskmouth 132kV Substation
- Uskmouth - New ConnectionEngland and Wales, StorageCustomer changed from ENSO GREEN HOLDINGS E LIMITED to AW1 ENERGY STORAGE LIMITED
- UskmouthEngland and Wales, StorageRestructured from 1 stage (230 MW connected) to 2 stages (230 MW from 30 Jun 2024, 120 MW from 30 Oct 2038)
- SolutiaEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Uskmouth 132kV to Uskmouth 132kV Substation)
- UskmouthEngland and Wales, StorageTechnology changed from Coal to Storage
- UskmouthEngland and Wales, StorageRenamed from Uskmouth Battery Energy Storage
- UskmouthEngland and Wales, StorageConnection point changed from Uskmouth 275kV Substation to Uskmouth 132kV Substation
- UskmouthEngland and Wales, StorageRenamed from Uskmouth
- UskmouthEngland and Wales, StorageConnection point changed from Uskmouth 132kV to Uskmouth 275kV Substation
- UskmouthEngland and Wales, StorageTechnology changed from Storage to Coal
- Uskmouth - New ConnectionEngland and Wales, StorageConnection point changed from Uskmouth 132kV to Uskmouth 275kV Substation
- UskmouthEngland and Wales, StorageCustomer changed from SIMEC USKMOUTH POWER LIMITED to USKMOUTH ENERGY STORAGE LIMITED
- UskmouthEngland and Wales, StorageTechnology changed from Coal to Storage
- SolutiaEngland and Wales, Thermal (gas, biomass, waste)Customer changed from DISTRICT ENERGY LIMITED to UK POWER RESERVE LIMITED
- Uskmouth - New ConnectionEngland and Wales, StorageRenamed from Uksmouth - New Connection
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?