Tod Point 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Net Zero Teesside Power Project | NET ZERO TEESSIDE POWER LIMITED | Thermal (gas, biomass, waste) | 860 | 30 Jul 2027 | Not stated | Consents Approved |
Recent changes
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT) to Gas (CCGT), Demand
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Apr 2026 to 30 Jul 2027 (+15 months)+15 mo
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Status changed from Awaiting Consents to Consents Approved
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Renamed from NZT Power Project
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Tod Point 275kV to Tod Point 275kV Substation)
- Net Zero Teesside Power ProjectEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?