Net Zero Teesside Power Project
NET ZERO TEESSIDE POWER LIMITED at Tod Point 275kV Substation
- Connection date
- 30 Jul 2027
- Gate
- Not stated
- Status
- Consents Approved
- Planning consent
- Granted 16 Feb 2024
The Net Zero Teesside Project (EN010103) · Source: Planning Inspectorate - Technology
- Gas (CCGT) + Demand
- Total capacity
- 860 MW
- Connected now
- 0 MW
- Still to connect
- 860 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001400
- In the register since
- June 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerTechnology changed from Gas (CCGT) to Gas (CCGT), Demand
- 29 Oct 2024 registerConnection date moved from 30 Apr 2026 to 30 Jul 2027 (+15 months)
- 29 Oct 2024 registerStatus changed from Awaiting Consents to Consents Approved
- 28 Nov 2023 registerRenamed from NZT Power Project
- 23 Dec 2022 registerSubstation name updated in the register (from Tod Point 275kV to Tod Point 275kV Substation)
- 29 Jun 2021 registerAdded to the register
Also at Tod Point 275kV Substation
Substation viewNo other projects in the register at this connection point.