Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Net Zero Teesside Power Project

NET ZERO TEESSIDE POWER LIMITED at Tod Point 275kV Substation

Connection date
30 Jul 2027
Gate
Not stated
Status
Consents Approved
Planning consent
Granted 16 Feb 2024
The Net Zero Teesside Project (EN010103) · Source: Planning Inspectorate
Technology
Gas (CCGT) + Demand
Total capacity
860 MW
Connected now
0 MW
Still to connect
860 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001400
In the register since
June 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 24 Dec 2024 register
    Technology changed from Gas (CCGT) to Gas (CCGT), Demand
  • 29 Oct 2024 register
    Connection date moved from 30 Apr 2026 to 30 Jul 2027 (+15 months)
  • 29 Oct 2024 register
    Status changed from Awaiting Consents to Consents Approved
  • 28 Nov 2023 register
    Renamed from NZT Power Project
  • 23 Dec 2022 register
    Substation name updated in the register (from Tod Point 275kV to Tod Point 275kV Substation)
  • 29 Jun 2021 register
    Added to the register

Also at Tod Point 275kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision for this project, from the Planning Inspectorate. NESO’s status can lag behind planning decisions, so the two may differ.