Thornton 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Thornton Facility | BALWEN LIMITED | Storage with solar or wind | 830 | 29 Oct 2027 | Not stated | Consents Approved |
| Thornton | IGP SOLAR 19 LIMITED | Storage with solar or wind | 500 | 31 Oct 2031 | Not stated | Scoping |
| Derwent Solar PV Array | ANESCO LIMITED | Solar | 160 | 31 May 2032 | Not stated | Scoping |
| Elmya Melbourne BESS | ELMYA RPC UK MELBOURNE LIMITED | Storage | 300 | 28 Oct 2033 | Gate 1 | Awaiting Consents |
Left the register since January 2021: Zenobe Thornton BESS (330 MW).
Recent changes
- Elmya Melbourne BESSEngland and Wales, StorageStage 1: Marked as Gate 1
- Elmya Melbourne BESSEngland and Wales, StorageStage 2: Marked as Gate 1
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Gate marking removed (was Gate 2)
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: 100 MW now connectedConnected
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Status changed from Under Construction/Commissioning to Built
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Given a Gate 2 connection offerGate 2
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Connection date moved from 25 Oct 2024 to 24 Sep 2025 (+11 months)+11 mo
- Thornton FacilityEngland and Wales, Storage with solar or windStage 2: Connection date moved from 23 Oct 2026 to 29 Oct 2027 (+12 months)+12 mo
- Thornton FacilityEngland and Wales, Storage with solar or windStage 3: Connection date moved from 27 Oct 2028 to 30 Nov 2028 (+1 month)+1 mo
- Thornton FacilityEngland and Wales, Storage with solar or windStage 4: Connection date moved from 28 Nov 2031 to 29 Oct 2032 (+11 months)+11 mo
- Elmya Melbourne BESSEngland and Wales, StorageRestructured from 1 stage (300 MW from 28 Oct 2033) to 2 stages (252 MW from 28 Oct 2033, 48 MW from 28 Oct 2039)
- Zenobe Thornton BESSEngland and Wales, StorageLeft the register (330 MW from 30 Oct 2035)330 MW
- Zenobe Thornton BESSEngland and Wales, StorageAdded to the registerNew
- Elmya Melbourne BESSEngland and Wales, StorageCustomer changed from ELMYA ENERGY UK 5 LIMITED to ELMYA RPC UK MELBOURNE LIMITED
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Jun 2024 to 25 Oct 2024 (+4 months)+4 mo
- Thornton FacilityEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Oct 2026 to 23 Oct 2026 (8 days earlier)
- Thornton FacilityEngland and Wales, Storage with solar or windStage 2: Status changed from Awaiting Consents to Consents Approved
- Thornton FacilityEngland and Wales, Storage with solar or windStage 3: Connection date moved from 1 Jul 2028 to 27 Oct 2028 (+4 months)+4 mo
- Thornton FacilityEngland and Wales, Storage with solar or windStage 3: Status changed from Awaiting Consents to Consents Approved
- Thornton FacilityEngland and Wales, Storage with solar or windNew stage added (530 MW from 28 Nov 2031)
- Thornton FacilityEngland and Wales, Storage with solar or windStage 1: Status changed from Awaiting Consents to Under Construction/Commissioning
- Elmya Melbourne BESSEngland and Wales, StorageAdded to the registerNew
- Derwent Solar PV ArrayEngland and Wales, SolarAdded to the registerNew
- Thornton FacilityEngland and Wales, Storage with solar or windRenamed from Thornton New Connection
- ThorntonEngland and Wales, Storage with solar or windAdded to the registerNew
- Thornton FacilityEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?