Thornton Facility
- Connection date
- 29 Oct 2027
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 930 MW
- Connected now
- 100 MW
- Still to connect
- 830 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001484
- In the register since
- June 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 100 | 0 | 100 | None | Not stated | Built |
| 2 | 0 | 100 | 200 | 29 Oct 2027 | Not stated | Consents Approved |
| 3 | 0 | 200 | 400 | 30 Nov 2028 | Not stated | Consents Approved |
| 4 | 0 | 530 | 930 | 29 Oct 2032 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Jul 2026 registerStage 1: Gate marking removed (was Gate 2)
- 26 Jun 2026 registerStage 1: 100 MW now connected
- 26 Jun 2026 registerStage 1: Status changed from Under Construction/Commissioning to Built
- 26 Jun 2026 registerStage 1: Given a Gate 2 connection offer
- 31 Oct 2025 registerStage 1: Connection date moved from 25 Oct 2024 to 24 Sep 2025 (+11 months)
- 31 Oct 2025 registerStage 2: Connection date moved from 23 Oct 2026 to 29 Oct 2027 (+12 months)
- 31 Oct 2025 registerStage 3: Connection date moved from 27 Oct 2028 to 30 Nov 2028 (+1 month)
- 31 Oct 2025 registerStage 4: Connection date moved from 28 Nov 2031 to 29 Oct 2032 (+11 months)
- 31 Oct 2023 registerStage 1: Connection date moved from 30 Jun 2024 to 25 Oct 2024 (+4 months)
- 31 Oct 2023 registerStage 2: Connection date moved from 31 Oct 2026 to 23 Oct 2026 (8 days earlier)
- 31 Oct 2023 registerStage 2: Status changed from Awaiting Consents to Consents Approved
- 31 Oct 2023 registerStage 3: Connection date moved from 1 Jul 2028 to 27 Oct 2028 (+4 months)
- 31 Oct 2023 registerStage 3: Status changed from Awaiting Consents to Consents Approved
- 31 Oct 2023 registerNew stage added (530 MW from 28 Nov 2031)
- 30 May 2023 registerStage 1: Status changed from Awaiting Consents to Under Construction/Commissioning
- 25 Feb 2022 registerRenamed from Thornton New Connection
- 29 Jun 2021 registerAdded to the register
Also at Thornton 400kV Substation
Substation view3 other projects, 1.8 GW still to connect at this substation in total.