Sandyknowe 132/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Sandy Knowe Wind Farm | SANDY KNOWE WIND FARM LIMITED | Onshore wind | 21.6 | 31 Oct 2027 | Gate 1 | Awaiting Consents |
Recent changes
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Marked as Gate 1
- Sandy Knowe Wind FarmSouth Scotland, Onshore windConnection point changed from Sandy Knowe Wind Farm 132kV Substation to Sandyknowe 132/33kV
- Sandy Knowe Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Sandy Knowe Wind Farm 132kV to Sandy Knowe Wind Farm 132kV Substation)
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 1: 86.4 MW now connectedConnected
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 1: Status changed from Under Construction/Commissioning to Built
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 1: Capacity changed from 51 MW to 86.4 MW
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 1: Connection date moved from 25 Feb 2022 to 17 May 2022 (+3 months)+3 mo
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Capacity changed from 39 MW to 21.6 MW
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 1 Nov 2023 to 31 Oct 2027 (+48 months)+48 mo
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Status changed from Consents Approved to Awaiting Consents
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 2 Apr 2024 to 1 Nov 2023 (−5 months)−5 mo
- Sandy Knowe Wind FarmSouth Scotland, Onshore windStage 2: Connection date moved from 4 Feb 2024 to 2 Apr 2024 (+2 months)+2 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?