Sandy Knowe Wind Farm
- Connection date
- 31 Oct 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 108 MW
- Connected now
- 86.4 MW
- Still to connect
- 21.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000345
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 86.4 | 0 | 86.4 | None | Not stated | Built |
| 2 | 0 | 21.6 | 108 | 31 Oct 2027 | Gate 1 | Awaiting Consents |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerStage 2: Marked as Gate 1
- 27 Sep 2024 registerConnection point changed from Sandy Knowe Wind Farm 132kV Substation to Sandyknowe 132/33kV
- 23 Dec 2022 registerSubstation name updated in the register (from Sandy Knowe Wind Farm 132kV to Sandy Knowe Wind Farm 132kV Substation)
- 28 Oct 2022 registerStage 1: 86.4 MW now connected
- 28 Oct 2022 registerStage 1: Status changed from Under Construction/Commissioning to Built
- 31 May 2022 registerStage 1: Capacity changed from 51 MW to 86.4 MW
- 31 May 2022 registerStage 1: Connection date moved from 25 Feb 2022 to 17 May 2022 (+3 months)
- 31 May 2022 registerStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- 31 May 2022 registerStage 2: Capacity changed from 39 MW to 21.6 MW
- 31 May 2022 registerStage 2: Connection date moved from 1 Nov 2023 to 31 Oct 2027 (+48 months)
- 31 May 2022 registerStage 2: Status changed from Consents Approved to Awaiting Consents
- 28 Sep 2021 registerStage 2: Connection date moved from 2 Apr 2024 to 1 Nov 2023 (−5 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 4 Feb 2024 to 2 Apr 2024 (+2 months)
Also at Sandyknowe 132/33kV
Substation viewNo other projects in the register at this connection point.